EOT assessment

I received an EOT on one of my project due to multiple delays caused by an architect. Perfect opportunity to learn how to assess them.

3910

John advised there is an example at the back of 3910:2013. Here is the excerpt:

Assessment

When it came to assessment, I could rather quickly to grasp the idea from the flowchart.
Speaking with a few of my colleagues I confirmed my understanding:

Work out their claim. Ensure that what we compensated the contractor for before ( for example in an agreed Variation that later caused the EOT claim) is not certified for the second time.
However, when I started prying again using AI, I received conflicting results

Further processing